work work work ... nothing but work Bautage No. 27-30 An eventful week lies behind us. At the same time, this was also the first week in which we start at himself really could! What remains is the realization that it was exactly the right decision three weeks to take a holiday!
But let's start (almost) all over again!
stand Tuesday by 10 clock of the site meeting with all suppliers on the program. To our surprise, were actually on time all the parties together ... except the power company, who came not know, but could not apologize and the civil contractors of the community "represented".
discussed in a few minutes, the catering and construction manager in our high-sounding Chinese trade, which could be done for everything. Our construction manager was noticeably tried to deliver the dubbing, which was fine with us :-). After a few minutes was the essential clarified. Only at one point there was a disagreement. Our construction manager discussed with the civil engineers of the municipality and the employees of the water works on who to close down for the service connections at the transfer point jurisdiction. Very traditionally the responsibility between the community, civil contractors Viebrock was pushed back and forth. In the heat of battle we lose out of the blue of the employees of the Waterworks ... without saying goodbye. An ugly and rather arrogant train, as we found ... But something has to accept, unfortunately, because the community is now at the longer times (monopoly) Lever is sitting. Ultimately remained the responsibility lie at Viebrock ... Our construction manager admitted defeat and does the work. These are usually (as the construction manager) never Viebrock and generally accessible by the supplier carried out ... but oh well ... we just make sure that it's done :-)
After this date was ticked off, we had only one transmission interval. Only toward the end of the dienstägtlichen Bautage then we could admire the finished wallpapered ceiling in the ground and completed filling.
it was Wednesday after a long time going on with backhoe Action (we had since the demolition of no more): After Monday, the company had delivered her Born excavator working device was, at last with the first chapter of house connections Go: Our small house was connected to the channel. The whole procedure took only painless but 6 hours.
After this work was done, we tingelte to the community to communicate this solemn that we are now connected to the channel .... tja .. who want to stop that charges. At least the employees of the municipality in contrast to their colleagues of the water works were very friendly.
Subsequently, we again had a short meeting with the civil engineers who works for our community. This is (conveniently) and the trench for the rest of the supply lines to create on our property and gave us his bid for the work. Since the offer price did not include any major surprises, it was quickly signed. . A big item on our to-do list less
Thursday then initially started quite innocently:
Our supervisor looked over yet just off operations to accommodate the transfer shaft of the channel closer look. At the same time we were able to clarify some open questions.
After talking it was then in the next hardware store. We ordered laminate samples arrived and after 1000 Hardware felt we wanted to stay at last set on a laminate type. Difficult wars, but TADAAAA: The winner is Elesgo Wellness Floor River Oak
The laminate even makes us like it so much that we decided to move it in all non-tiled rooms.
Since the laminate has a built-in sound insulation, we need than "just" to demonstrate even a PE vapor barrier under it.
walked in our shopping cart then 2 bucket of primer ... so that it can soon start to create the walls ;-).
Being back on the site, we have a total of 3 Transportation welcome: electricians, tilers and grouting (this is called soo?) for the clinker had arrived and busy at work!
Since the floor but was already accessible, that it was for us the matter with the acrylic joints! A huge mess ;-) But after some trouble in one of the children we had the hang of it quickly and developed an incredibly efficient technique: Pull joint with much feeling:
Step 1 , Step 2: Tighten with a wet brush, and step 3: the finger smooth out the joint (and the mess the previous unvorichtigen eliminate) :-)
Appointed joint master remained fairly quickly located in the corner. This we would only be for more delicate joint work (shower,) recommend. For large and long so that the joints will take far too long.
After a few hours then done: our bedroom and the two children were ready! But the craftsmen were busy: (! Schöön!)
The wall tiles in the bathroom were finished, the living room was ferig tiles (also schööön) and the fuse box was mounted (nuja. .. nice that he's there) :-)
Also runs (heating up the floor heating) the heating, the clinker was grouted done and we have a first injury occurred: An edge in the plaster (construction but already knows notice)
The
this Friday should not be less exciting:
early hopped out of bed we went for our first giant furniture shopping to Ikea! After a delicious
Ikeafrühstück was Pax, various Malm and three Varieanten Hemnes and ordered a delivery date (in 2 weeks ... Uiuiui) agreed. Also ended up (as it should be otherwise at Ikea) .... many planned and a few unplanned things in the shopping basket, so we made it to the end to several thousand € while the cart was sooo empty! But no matter! We look forward, especially on our Pax, which is right with the new doors so Tonnes times sharp lookout :-)
was on the way back there again in a DIY store to buy film to ... Finally, planned for tomorrow, priming the walls nothing stand in your way.
but once at home no time to Aussruhen: it was diligently acrylic and grouted as planned, following in two rooms slide designed.
allowed between, we enjoy the finished bathroom tiles ... only entering was strictly forbidden:
... but sooo beautiful!
Equally, electricians complete their work almost ....
... only if the correct spelling, there is still a little improvement:
In this sense, we adopt, and of these busy days of the busy weekend! :-)