Our House is gettin 'dirty

construction day No. 17

week new, new crafters!

Today we received a so-called outer wall Egalisierungsanstrich. This is a unique coating, drying, weather-related processing and color differences in the Putzfäche output slightly. is supposed to look all nice and smooth :-)


The plaster through the paint more evenly and a little brighter now
(you can see in pictures but not so hot)

was also started today with the interior plaster. This is perhaps ne mess ;-) After the plasterers had left the site in the evening, a round of mud wrestling would have been quite loose in there. For such a work environment plasterers are really not envy ... but wat dat must have!

The exterior walls on the first floor and some interior walls on the ground now shine in the sympathetic muddy gray.

mud not only on the wall:
mud is everywhere!

The containers are gone, a silo is now here!


Since this week in Hesse is a short work week (Corpus Christi), are probably the next few days only "inside the walls plastered finish. The free Thursday, we then want to use for the second Ansrich the roof overhangs. Because next week, the scaffolding is removed, we have planned a possibly necessary third coat for the coming weekend.

Would be great if the weather would play ... present the predictions of view but really good!